Excavation Zanja Y/O Pozo Terraplénico sin Clasificación
- Code
- U02ZE070
- Public ID
- OC0058ee63d0
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- October 8, 2026
Components sum €6.35 · Unit price €6.35/m3
Capataz
O01A020· 0.02 h
€0.36
€17.97/h
0.02 h / 1 m3 parent
Peón ordinario
O01A070· 0.02 h
€0.33
€16.68/h
0.02 h / 1 m3 parent
Goma-2 D=40 mm.
P01XG010· 0.025 kg
€0.09
€3.46/kg
0.025 kg / 1 m3 parent
Nagolita a granel
P01XN010· 0.025 kg
€0.03
€1.23/kg
0.025 kg / 1 m3 parent
Detonador eléctrico
P01XD010· 0.01 ud.
€0.01
€1.30/ud.
0.01 ud. / 1 m3 parent
Hilo de conexión
P01XC030· 0.15 m
€0.02
€0.11/m
0.15 m / 1 m3 parent
Cordón detonante 12 gr.
P01XC010· 0.01 m
€0.00
€0.49/m
0.01 m / 1 m3 parent
Excav.hidr.neumáticos 100 CV
M05EN030· 0.075 h
€3.57
€47.57/h
0.075 h / 1 m3 parent
Martillo rompedor hidrá. 600 kg.
M06MR230· 0.03 h
€0.25
€8.37/h
0.03 h / 1 m3 parent
Compr.port. diesel m.p.10m3/min
M06CM040· 0.02 h
€0.23
€11.62/h
0.02 h / 1 m3 parent
Bomba autoas.di.ag.lim.b.p.40kW
M01DA320· 0.02 h
€0.33
€16.37/h
0.02 h / 1 m3 parent
Pala carg.neumát. 85 CV/1,2m3
M05PN010· 0.01 h
€0.40
€40.33/h
0.01 h / 1 m3 parent
Camión basculante 4x4 14 t.
M07CB020· 0.02 h
€0.73
€36.65/h
0.02 h / 1 m3 parent