U03HP240Unit price
Concrete HM/HA-30/B/40/X0. Column. Manual Formwork Without Shoring.
Key Details
- Code
- U03HP240
- Public ID
- OC036bf7d0bb
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- October 9, 2026
Composition (BC3 recipe)
Components sum €120.01 · Unit price €120.01/m3
Oficial primera encofradores
O01BE010· 0.45 h
€8.38
€18.63/h
0.45 h / 1 m3 parent
Ayudante encofradores
O01BE020· 0.45 h
€8.02
€17.83/h
0.45 h / 1 m3 parent
Hormigón HM-30/B/40/X0 central
P01HCM007· 1 m3
€103.00
€103.00/m3
1 m3 / 1 m3 parent
Vibrador hormigón gasolina 75 mm
M10HV080· 0.25 h
€0.61
€2.43/h