Marco HA-30, height 8 m, volume 5.5 m, height 0.5 m
- Code
- U03BA070
- Public ID
- OC05a7f705fd
- Category
- Materials
- Subcategory
- general
- Unit
- m
- Resource Type
- Unit price
- Last Updated
- October 9, 2026
Components sum €6,730.62 · Unit price €6,934.45/m
Capataz
O01A020· 8.35 h
€150.05
€17.97/h
8.35 h / 1 m parent
Oficial primera
O01A030· 16.701 h
€295.77
€17.71/h
16.701 h / 1 m parent
AYUDANTE
O01A050· 0.552 h
€7.95
€14.40/h
0.552 h / 1 m parent
Peón ordinario
O01A070· 16.701 h
€278.57
€16.68/h
16.701 h / 1 m parent
Oficial primera encofradores
O01BE010· 14.74 h
€274.61
€18.63/h
14.74 h / 1 m parent
Ayudante encofradores
O01BE020· 14.74 h
€262.81
€17.83/h
14.74 h / 1 m parent
Oficial primera ferrallista
O01BF030· 7.936 h
€147.85
€18.63/h
7.936 h / 1 m parent
Ayudante ferrallista
O01BF040· 7.936 h
€141.50
€17.83/h
7.936 h / 1 m parent
Tablero encofrar 22 mm. 4 p.
M12EM030· 19 m2
€45.79
€2.41/m2
19 m2 / 1 m parent
Tablón pino gallego 76x205mm>2,5m
P01EB010· 0.327 m³
€133.47
€408.16/m³
0.327 m³ / 1 m parent
Aditivo desencofrante
P01DC010· 6.62 kg
€9.47
€1.43/kg
6.62 kg / 1 m parent
Puntas 20x100
P01UC030· 0.662 kg
€0.81
€1.23/kg
0.662 kg / 1 m parent
Encof.panel metal.5/10 m2. 50 p.
M12EF020· 14.1 m²
€7.76
€0.55/m²
14.1 m² / 1 m parent
Fleje para encofrado metálico
M12EF040· 7.05 m
€1.41
€0.20/m
7.05 m / 1 m parent
Ferralla elaborada taller industrial acero barra corrugada, UNE-EN10080 B500S/SD varios diámetros
P03AC210· 2064.213 kg
€2,477.06
€1.20/kg
2064.213 kg / 1 m parent
Alambre atar 1,30 mm.
P03AA020· 9.92 kg
€14.28
€1.44/kg
9.92 kg / 1 m parent
HNE-15/P/32 central
P01HDN040· 0.92 m³
€82.80
€90.00/m³
0.92 m³ / 1 m parent
Hormigón HM-30/B/20/X0 central
P01HCM008· 19.839 m³
€2,043.42
€103.00/m³
19.839 m³ / 1 m parent
Camión con grúa 6 t.
M07CG010· 3.304 h
€168.31
€50.94/h
3.304 h / 1 m parent
Vibrador horm.neumático 100 mm.
M10HV030· 3.593 h
€4.56
€1.27/h
3.593 h / 1 m parent
Compresor portátil diesel media presión 2 m3/min
M06CM030· 3.593 h
€8.98
€2.50/h
3.593 h / 1 m parent
Autob.hormig.<40m3, pluma<32m
M01HA010· 0.815 h
€173.19
€212.50/h
0.815 h / 1 m parent
Alqu./dÃa cimbra tub.3 m/1000 kg
M12EZ010· 1.32 m³
€0.20
€0.15/m³
1.32 m³ / 1 m parent