S03CJT080Unit price
Supply/Install. 2 Months. Scaffolding h<8 m.
Key Details
- Code
- S03CJT080
- Public ID
- OC10a3f20d00
- Category
- Materials
- Subcategory
- Unit
- m2
- Resource Type
- Unit price
- Last Updated
- October 11, 2026
Composition (BC3 recipe)
Components sum €11.34 · Unit price €11.34/m2
m2. alq. andamio acero galvanizado
M12AA680· 60 día
€3.00
€0.05/día
60 día / 1 m2 parent
Montaje y desm. and. h<8 m. Europeo
M12AA635· 1 m²
€6.96
€6.96/m²
1 m² / 1 m2 parent
m2. alq. red mosquitera andamios
M12AA690· 30 día
€0.30
€0.01/día
30 día / 1 m2 parent
Montaje y desm. red andam.
M12AA700· 1 m²
€1.08
€1.08/m²
1 m² / 1 m2 parent