F04B180Material
Framing Moulding Triple 0.6
Key Details
- Code
- F04B180
- Public ID
- OC1129c03435
- Category
- Materials
- Subcategory
- Unit
- ud.
- Resource Type
- Material
- Last Updated
- October 11, 2026
Composition (BC3 recipe)
Components sum €714.59 · Unit price €714.59/ud.
HORMIGON 25 N/MM2, EN PLANTA, ARIDO 20
F04H220· 0.66 m³
€75.53
€114.44/m³
0.66 m³ / 1 ud. parent
MAMPOSTERIA HORMIGONADA EN ALZADO DE MUROS
F04M030· 3.2 m³
€593.47
€185.46/m³
3.2 m³ / 1 ud. parent
EXTENDIDO DE TIERRAS
F04E140· 8.32 m³
€2.33
€0.28/m³
8.32 m³ / 1 ud. parent
EXCAVACION MECANICA ZANJA
F04E110· 8.32 m³
€43.26
€5.20/m³
8.32 m³ / 1 ud. parent
Compare across the category