E05HVA020Material
Plank Formwork HA-25/F/20/X0 Wooden Framed
Key Details
- Code
- E05HVA020
- Public ID
- OC11f76a9fb2
- Category
- Materials
- Subcategory
- Unit
- m³
- Resource Type
- Material
- Last Updated
- October 11, 2026
Composition (BC3 recipe)
Components sum €569.19 · Unit price €1,024.74/m³
Oficial primera encofradores
O01BE010· 0.125 h
€2.33
€18.63/h
0.125 h / 1 m³ parent
Ayudante encofradores
O01BE020· 0.125 h
€2.23
€17.83/h
0.125 h / 1 m³ parent
Hormigón HA-25/F/20/X0 central
P01HCA071· 1.05 m³
€102.90
€98.00/m³
1.05 m³ / 1 m³ parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.1 h
€0.30
€3.02/h
0.1 h / 1 m³ parent
ENCOFRADO VISTO MADERA EN JÁCENAS / ZUNCHOS
E05HVE020· 9.17 m²
€460.98
€50.27/m²
9.17 m² / 1 m³ parent
ACERO CORRUGADO SOLDABLE B500 S/SD OBRA+OBRA
E04AB0040· 0.18 kg
€0.45
€2.49/kg
0.18 kg / 1 m³ parent
Compare across the category