Excavation of Foundations with Rock Explosives
- Code
- U02AD140
- Public ID
- OC12490b9e80
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- October 11, 2026
Components sum €18.58 · Unit price €18.91/m3
Capataz
O01A020· 0.025 h
€0.45
€17.97/h
0.025 h / 1 m3 parent
Oficial primera
O01A030· 0.12 h
€2.13
€17.71/h
0.12 h / 1 m3 parent
AYUDANTE
O01A050· 0.12 h
€1.73
€14.40/h
0.12 h / 1 m3 parent
Goma-2 D=40 mm.
P01XG010· 0.15 kg
€0.52
€3.46/kg
0.15 kg / 1 m3 parent
Nagolita en cartuchos
P01XN020· 0.3 kg
€0.54
€1.81/kg
0.3 kg / 1 m3 parent
Detonador eléctrico
P01XD010· 0.1 ud.
€0.13
€1.30/ud.
0.1 ud. / 1 m3 parent
Hilo de conexión
P01XC030· 1 m
€0.11
€0.11/m
1 m / 1 m3 parent
Carro perf.hidr.s/ruedas 100 mm.
M06VR110· 0.12 h
€8.80
€73.30/h
0.12 h / 1 m3 parent
Excav.hidr.cadenas 195 CV
M05EC030· 0.045 h
€2.94
€65.36/h
0.045 h / 1 m3 parent
Martillo rompedor hidrá. 1000 kg
M06MR240· 0.045 h
€0.50
€11.12/h
0.045 h / 1 m3 parent
Camión basculante 4x4 14 t.
M07CB020· 0.02 h
€0.73
€36.65/h
0.02 h / 1 m3 parent