Forged Rigid Steel Bov. Cer. (HA-25)
- Code
- 05FUA00011
- Public ID
- OC140016307d
- Category
- Materials
- Subcategory
- Unit
- m²
- Resource Type
- Labor
- Last Updated
- October 12, 2026
Components sum €24.43 · Unit price €28.24/m²
OF. 1¦ FERRALLISTA
TO00600· 0.026 h
€0.39
€15.12/h
0.026 h / 1 m² parent
OFICIAL 1¦
TO02100· 0.063 h
€0.95
€15.12/h
0.063 h / 1 m² parent
PEON ESPECIAL
TP00100· 0.306 h
€4.36
€14.26/h
0.306 h / 1 m² parent
ACERO B 500 S
CA00320· 1 kg
€0.77
€0.77/kg
1 kg / 1 m² parent
ACERO ELECTROSOLDADO ME B 500 T EN MALLA
CA00620· 0.99 kg
€1.19
€1.20/kg
0.99 kg / 1 m² parent
BOVEDILLA CERAMICA
CB00500· 5.15 ud.
€4.53
€0.88/ud.
5.15 ud. / 1 m² parent
HORMIGÓN HA-25/P/20/IIa, SUMINISTRADO
CH02920· 0.105 m³
€6.76
€64.36/m³
0.105 m³ / 1 m² parent
MADERA DE PINO EN TABLON
CM00300· 0.001 m³
€0.28
€278.87/m³
0.001 m³ / 1 m² parent
VIGUETA AUTORRESISTENTE DE ARMADURA RIGIDA
CV00100· 1.397 m
€4.79
€3.43/m
1.397 m / 1 m² parent
VIBRADOR
MV00100· 0.07 h
€0.11
€1.51/h
0.07 h / 1 m² parent
PEQUE¥O MATERIAL
WW00400· 1 ud.
€0.30
€0.30/ud.
1 ud. / 1 m² parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.