03HRM80060Material
Reinforced Concrete Wall with Ha-25/B/15/IIa B400S in Containing Wall 1C. With Pump
Key Details
- Code
- 03HRM80060
- Public ID
- OC15b3e745b8
- Category
- Materials
- Subcategory
- general
- Unit
- m³
- Resource Type
- Material
- Last Updated
- October 12, 2026
Composition (BC3 recipe)
Components sum €357.50 · Unit price €293.41/m³
BOMBA DE HORMIGONAR
MB00200· 0.15 h
€8.38
€55.84/h
0.15 h / 1 m³ parent
ACERO EN BARRAS CORRUGADAS B400S EN CIMENT.
03ACC00010· 60 kg
€81.00
€1.35/kg
60 kg / 1 m³ parent
ENCOFRADO METÁLICO 1 C. EN MURO DE CONTENCIÓN
03ERT80050· 2.9 m²
€187.14
€64.53/m²
2.9 m² / 1 m³ parent
HORMIGÓN HA-25/B/15/IIa EN MUROS DE CONTENCIÓN
03HAM80030· 1 m³
€80.98
€80.98/m³
1 m³ / 1 m³ parent