E08KT060Material
Overcoat > 3 m
Key Details
- Code
- E08KT060
- Public ID
- OC1628d131d0
- Category
- Materials
- Subcategory
- Unit
- m²
- Resource Type
- Material
- Last Updated
- October 12, 2026
Composition (BC3 recipe)
Components sum €23.46 · Unit price €24.05/m²
Oficial primera
O01A030· 0.42 h
€7.44
€17.71/h
0.42 h / 1 m² parent
AYUDANTE
O01A050· 0.21 h
€3.02
€14.40/h
0.21 h / 1 m² parent
Peón ordinario
O01A070· 0.05 h
€0.83
€16.68/h
0.05 h / 1 m² parent
Mortero fratas.decorativo hidro
P04RD070· 13 kg
€5.20
€0.40/kg
13 kg / 1 m² parent
Agua
P01DW010· 0.008 m3
€0.01
€0.91/m3
0.008 m3 / 1 m² parent
Montaje y desmontaje andamio 15 m<h<20 m. Europeo
M12AA660· 1 m²
€6.96
€6.96/m²
1 m² / 1 m² parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.