Structural Conventional Concrete HA-30/F/20/XC2 Cim. V.Autobomba Zap.+V.Arr.
- Code
- E04CZA080
- Public ID
- OC184b5cae4a
- Category
- Materials
- Subcategory
- Unit
- m³
- Resource Type
- Material
- Last Updated
- October 13, 2026
Components sum €382.31 · Unit price €214.36/m³
Oficial primera encofradores
O01BE010· 0.2 h
€3.73
€18.63/h
0.2 h / 1 m³ parent
Ayudante encofradores
O01BE020· 0.2 h
€3.57
€17.83/h
0.2 h / 1 m³ parent
Oficial primera ferrallista
O01BF030· 0.15 h
€2.79
€18.63/h
0.15 h / 1 m³ parent
Ayudante ferrallista
O01BF040· 0.15 h
€2.67
€17.83/h
0.15 h / 1 m³ parent
Hormigón HA-30/F/20/XC2 central
P01HCA090· 1.1 m³
€113.30
€103.00/m³
1.1 m³ / 1 m³ parent
Autob.hormig.<40m3, pluma<32m
M01HA010· 0.05 h
€10.63
€212.50/h
0.05 h / 1 m³ parent
Desplazamiento autobomba
M01HA070· 1.5 h
€179.02
€119.35/h
1.5 h / 1 m³ parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.2 h
€0.60
€3.02/h
0.2 h / 1 m³ parent
ACERO CORRUGADO SOLDABLE B400 S/SD TALLER INDUSTRIAL+OBRA
E04AB040· 40 kg
€66.00
€1.65/kg
40 kg / 1 m³ parent