VDOT-2026-STAUNTON-505SD20-0039Unit price
GUARDRAIL TER.SITE PREPARATION VDOT Staunton district February 1, 2024 through March 1, 2026 average unit price
VDOT district averages; district STAUNTON; period February 1, 2024 through March 1, 2026; generated 6/1/2026 8:56:32 AM; minimum 1525; maximum 4200
guardrailsitepreparationvdotpriceaveragestaunton
Key Details
- Code
- VDOT-2026-STAUNTON-505SD20-0039
- Public ID
- OC3dd3e61f07
- Category
- Materials
- Subcategory
- Unit
- ea
- Resource Type
- Unit price
- Last Updated
- August 19, 2026
Composition (BC3 recipe)
Components sum $1,928.57 · Unit price $1,928.57/ea
GUARDRAIL TER.SITE PREPARATION VDOT Staunton district February 1, 2024 through March 1, 2026 average unit price
— · ea
$1,928.57
~100%
priced unit (no recipe tree)