E05HSA260Material
HA-30/F/20/XC3 Column Wood Formwork
columnha30f20xc3formworkwood
Key Details
- Code
- E05HSA260
- Public ID
- OC4ec190a576
- Category
- Materials
- Subcategory
- Unit
- m³
- Resource Type
- Material
- Last Updated
- October 10, 2026
Composition (BC3 recipe)
Components sum €667.60 · Unit price €674.81/m³
Oficial primera encofradores
O01BE010· 0.25 h
€4.66
€18.63/h
0.25 h / 1 m³ parent
Ayudante encofradores
O01BE020· 0.25 h
€4.46
€17.83/h
0.25 h / 1 m³ parent
Hormigón HA-30/F/20/XC3 central
P01HCA102· 1.05 m³
€109.20
€104.00/m³
1.05 m³ / 1 m³ parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.1 h
€0.30
€3.02/h
0.1 h / 1 m³ parent
ENCOFRADO MADERA EN PILARES 4 POSTURAS
E05HSD010· 13.33 m²
€349.78
€26.24/m²
13.33 m² / 1 m³ parent
ACERO CORRUGADO SOLDABLE B500 S/SD OBRA+OBRA
E04AB0040· 80 kg
€199.20
€2.49/kg
80 kg / 1 m³ parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.