F04C080Material
Double Concrete Pipe 0.6 M
Key Details
- Code
- F04C080
- Public ID
- OCdf612f26a6
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Material
- Last Updated
- August 2, 2026
Composition (BC3 recipe)
Components sum €200.80 · Unit price €212.88/m
Oficial primera
O01A030· 0.21 h
€3.72
€17.71/h
0.21 h / 1 m parent
Peón ordinario
O01A070· 2.1 h
€35.03
€16.68/h
2.1 h / 1 m parent
EXCAVACION MECANICA ZANJA
F04E110· 1.8 m³
€9.36
€5.20/m³
1.8 m³ / 1 m parent
Tubo de hormigón machiembrado de 40 cm
P41M2830· 2 m
€25.60
€12.80/m
2 m / 1 m parent
HORMIGÓN 20 N/MM2. IN SITU ÁRIDO 40
F04H210· 1.1 m³
€126.59
€115.08/m³
1.1 m³ / 1 m parent
EXTENDIDO DE TIERRAS
F04E140· 1.8 m³
€0.50
€0.28/m³
1.8 m³ / 1 m parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.