Well for Pipe, D= 80 cm.
- Code
- U04FPP020
- Public ID
- OCe019d0a5d3
- Category
- Materials
- Subcategory
- Unit
- ud
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Components sum €771.70 · Unit price €772.48/ud
Capataz
O01A020· 1.442 h
€25.91
€17.97/h
1.442 h / 1 ud parent
Oficial primera
O01A030· 0.625 h
€11.07
€17.71/h
0.625 h / 1 ud parent
Peón ordinario
O01A070· 0.625 h
€10.43
€16.68/h
0.625 h / 1 ud parent
Oficial primera encofradores
O01BE010· 7.048 h
€131.30
€18.63/h
7.048 h / 1 ud parent
Ayudante encofradores
O01BE020· 7.048 h
€125.67
€17.83/h
7.048 h / 1 ud parent
Encof.panel metal.5/10 m2. 50 p.
M12EF020· 11.34 m²
€6.24
€0.55/m²
11.34 m² / 1 ud parent
Tablero encofrar 22 mm. 4 p.
M12EM030· 5.28 m2
€12.72
€2.41/m2
5.28 m2 / 1 ud parent
Tablón pino gallego 76x205mm>2,5m
P01EB010· 0.116 m³
€47.35
€408.16/m³
0.116 m³ / 1 ud parent
Aditivo desencofrante
P01DC010· 3.324 kg
€4.75
€1.43/kg
3.324 kg / 1 ud parent
Puntas 20x100
P01UC030· 0.332 kg
€0.41
€1.23/kg
0.332 kg / 1 ud parent
Fleje para encofrado metálico
M12EF040· 5.37 m
€1.07
€0.20/m
5.37 m / 1 ud parent
Hormigón HM-20/B/20/X0 central
P01HCM003· 3.483 m³
€327.40
€94.00/m³
3.483 m³ / 1 ud parent
Vibrador horm.neumático 100 mm.
M10HV030· 0.625 h
€0.79
€1.27/h
0.625 h / 1 ud parent
Compresor portátil diesel media presión 2 m3/min
M06CM030· 0.625 h
€1.56
€2.50/h
0.625 h / 1 ud parent
Autob.hormig.<40m3, pluma<32m
M01HA010· 0.306 h
€65.03
€212.50/h
0.306 h / 1 ud parent