E03APB020Unit price
Solera Cono Pozo D=100/60 cm.h=60
soleraconopozod10060cmh60
Key Details
- Code
- E03APB020
- Public ID
- OCe840ee3e3b
- Category
- Materials
- Subcategory
- Unit
- ud.
- Resource Type
- Unit price
- Last Updated
- July 30, 2026
Composition (BC3 recipe)
Components sum €93.14 · Unit price €148.01/ud.
Oficial primera
O01A030· 1.8 h
€31.88
€17.71/h
1.8 h / 1 ud. parent
Peón especializado
O01A060· 0.9 h
€15.24
€16.93/h
0.9 h / 1 ud. parent
HL-150/B/20 central
P01HDL020· 0.248 m³
€22.32
€90.00/m³
0.248 m³ / 1 ud. parent
ME 150X300 ø 5-5 6000X2200 150/150-125/125-300 B500T UNE-EN 10008
P03AM500· 3.15 m²
€11.50
€3.65/m²
3.15 m² / 1 ud. parent
Ladrillo perforado tosco 25x12x7
P01LT020· 0.332 ud
€0.05
€0.14/ud
0.332 ud / 1 ud. parent
Mortero cemento gris M-5
P01MC120· 0.166 m3
€10.79
€64.98/m3
0.166 m3 / 1 ud. parent
Mortero cemento gris M-7,5
P01MC110· 0.02 m³
€1.36
€67.94/m³
0.02 m³ / 1 ud. parent