E17DA020Unit price
Drainage Sump 102x102x51cm
Key Details
- Code
- E17DA020
- Public ID
- OCe9e8a65c10
- Category
- Materials
- Subcategory
- Unit
- ud
- Resource Type
- Unit price
- Last Updated
- July 31, 2026
Composition (BC3 recipe)
Components sum €169.23 · Unit price €177.43/ud
Oficial primera
O01A030· 2.7 h
€47.82
€17.71/h
2.7 h / 1 ud parent
Peón especializado
O01A060· 2.7 h
€45.71
€16.93/h
2.7 h / 1 ud parent
Horm.elem. no resist.HM-10/B/32 central
P01HD070· 0.15 m³
€6.75
€44.97/m³
0.15 m³ / 1 ud parent
Ladrillo perforado tosco 25x12x7
P01LT020· 68 ud
€9.52
€0.14/ud
68 ud / 1 ud parent
Mortero 1/6 de central (M-5)
P01MC040· 0.008 m³
€0.39
€48.67/m³
0.008 m³ / 1 ud parent
Tapa cuadrada HA e=8cm 120x120cm
P02AC100· 1 ud
€55.79
€55.79/ud
1 ud / 1 ud parent
Grava 40/80 mm.
P01AG150· 0.25 m³
€3.00
€11.99/m³
0.25 m³ / 1 ud parent
Material auxiliar
%50500· 0.05 %
€0.25
€5.00/%
0.05 % / 1 ud parent