U03BC040Unit price
Framing Steel Frame 2.00x2.50 m.
Key Details
- Code
- U03BC040
- Public ID
- OCedee13f7eb
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Composition (BC3 recipe)
Components sum €787.12 · Unit price €942.12/m
Capataz
O01A020· 0.12 h
€2.16
€17.97/h
0.12 h / 1 m parent
Oficial primera
O01A030· 0.42 h
€7.44
€17.71/h
0.42 h / 1 m parent
Peón especializado
O01A060· 0.84 h
€14.22
€16.93/h
0.84 h / 1 m parent
Hormigón HM-20/B/20/X0 central
P01HCM003· 0.33 m³
€31.02
€94.00/m³
0.33 m³ / 1 m parent
Arena de río 0/5 mm.
P01AA030· 0.22 m3
€3.63
€16.50/m3
0.22 m3 / 1 m parent
Marco prefabricado hormigón armado 2,00x2,00 m.
P03CB040· 1 m
€565.00
€565.00/m
1 m / 1 m parent
Grúa telescópica autoprop. 180t.
M02GE120· 0.42 h
€163.65
€389.65/h
0.42 h / 1 m parent