Pre-Engineered Arch 8.5x4.95m
- Code
- U03BE060
- Public ID
- OCee9b1377ad
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Components sum €2,111.49 · Unit price €2,111.49/m
Capataz
O01A020· 1.9 h
€34.14
€17.97/h
1.9 h / 1 m parent
Oficial primera
O01A030· 4.8 h
€85.01
€17.71/h
4.8 h / 1 m parent
Peón ordinario
O01A070· 6.2 h
€103.42
€16.68/h
6.2 h / 1 m parent
Bóveda H.A. 8,50x4,95 m 7,78 t/m
P02TB170· 1 m
€1,423.42
€1,423.42/m
1 m / 1 m parent
L.oxiasf.3kg/m2 LO-30-FV(60g/m2)
P06BL030· 1.1 m²
€3.56
€3.24/m²
1.1 m² / 1 m parent
Lámina geot. PP-110 g/m2
P06BG250· 4.6 m²
€3.22
€0.70/m²
4.6 m² / 1 m parent
Hormigón HM-25/B/20/X0 central
P01HCM006· 0.1 m³
€9.70
€97.00/m³
0.1 m³ / 1 m parent
Tablero encofrar 17 mm. 4 p.
M12EM040· 0.4 m²
€0.89
€2.22/m²
0.4 m² / 1 m parent
Zahorra natural sin clasif. IP<6
P01AD050· 34.232 t
€172.87
€5.05/t
34.232 t / 1 m parent
Grúa telescópica autoprop. 25 t.
M02GE020· 2.5 h
€260.43
€104.17/h
2.5 h / 1 m parent
Rodillo v.dúplex 55cm 800 kg.man
M08RL010· 0.7 h
€3.95
€5.64/h
0.7 h / 1 m parent
Rodillo vibr.autopr.mixto 7 t.
M08RN020· 0.28 h
€2.78
€9.94/h
0.28 h / 1 m parent
Retrocargadora neum. 50 CV
M05RN010· 0.28 h
€8.10
€28.94/h
0.28 h / 1 m parent