In Situ Horizontal Slab c=25+5, Interbeams 70Ccm Polystyrene Subbase
- Code
- E05HFH360
- Public ID
- OCeebb093a8a
- Category
- Materials
- Subcategory
- Unit
- m²
- Resource Type
- Material
- Last Updated
- July 30, 2026
Components sum €88.71 · Unit price €90.42/m²
Oficial primera encofradores
O01BE010· 0.6 h
€11.18
€18.63/h
0.6 h / 1 m² parent
Ayudante encofradores
O01BE020· 0.6 h
€10.70
€17.83/h
0.6 h / 1 m² parent
Hormigón HA-25/F/20/X0 central
P01HCA071· 0.099 m³
€9.70
€98.00/m³
0.099 m³ / 1 m² parent
Bovedilla poliestireno 60 cm/subbase poliestireno.
P03BP110· 6.67 ud.
€6.87
€1.03/ud.
6.67 ud. / 1 m² parent
ME 200X300 ø 5-5 6000X2200 150/150-100/100-400 B500T UNE-EN 10008
P03AM490· 1.1 m²
€4.15
€3.77/m²
1.1 m² / 1 m² parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.2 h
€0.60
€3.02/h
0.2 h / 1 m² parent
ACERO CORRUGADO SOLDABLE B500 S/SD OBRA+OBRA
E04AB0040· 12 kg
€29.88
€2.49/kg
12 kg / 1 m² parent
ENCOFRADO MADERA FORJADO RETICULAR PLANO
E05HRE010· 1 m²
€15.63
€15.63/m²
1 m² / 1 m² parent