E05HFH320Material
In Situ Sloped Slab with Ceramic Tile
concretereinforcedslopedceramicflooring
Key Details
- Code
- E05HFH320
- Public ID
- OCf000b25641
- Category
- Materials
- Subcategory
- Unit
- m²
- Resource Type
- Material
- Last Updated
- July 30, 2026
Composition (BC3 recipe)
Components sum €76.65 · Unit price €79.58/m²
Oficial primera encofradores
O01BE010· 0.8 h
€14.90
€18.63/h
0.8 h / 1 m² parent
Ayudante encofradores
O01BE020· 0.8 h
€14.26
€17.83/h
0.8 h / 1 m² parent
Bovedilla cerámica 60x20x25cm
P03BC095· 6 ud.
€14.52
€2.42/ud.
6 ud. / 1 m² parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.2 h
€0.60
€3.02/h
0.2 h / 1 m² parent
ACERO CORRUGADO SOLDABLE B500 S/SD OBRA+OBRA
E04AB0040· 12 kg
€29.88
€2.49/kg
12 kg / 1 m² parent
ENCOFRADO FORJADO UNIDIRECCIONAL CONTÍNUO
E05HFE030· 0.1 m²
€2.49
€24.91/m²
0.1 m² / 1 m² parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.