U03HCO120Unit price
HM/HA-20/B/40/X0. Exposed Wall Column
Key Details
- Code
- U03HCO120
- Public ID
- OCf1655cfbde
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Composition (BC3 recipe)
Components sum €115.28 · Unit price €115.28/m3
Capataz
O01A020· 0.048 h
€0.86
€17.97/h
0.048 h / 1 m3 parent
Oficial primera
O01A030· 0.12 h
€2.13
€17.71/h
0.12 h / 1 m3 parent
Peón especializado
O01A060· 0.24 h
€4.06
€16.93/h
0.24 h / 1 m3 parent
Hormigón HM-20/B/40/X0 central
P01HCM001· 1 m³
€94.00
€94.00/m³
1 m³ / 1 m3 parent
Vibrador hormigón gasolina 75 mm
M10HV080· 0.12 h
€0.29
€2.43/h
0.12 h / 1 m3 parent
Autob.hormig.<40m3, pluma<32m
M01HA010· 0.06 h
€12.75
€212.50/h
0.06 h / 1 m3 parent
Desplazamiento autobomba
M01HA040· 0.01 h
€1.19
€119.35/h
0.01 h / 1 m3 parent