U04NA090Unit price
Natural Filling Sand
Key Details
- Code
- U04NA090
- Public ID
- OCf1bdc661d6
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Composition (BC3 recipe)
Components sum €26.43 · Unit price €26.43/m3
Capataz
O01A020· 0.06 h
€1.08
€17.97/h
0.06 h / 1 m3 parent
Peón ordinario
O01A070· 0.04 h
€0.67
€16.68/h
0.04 h / 1 m3 parent
Zahorra nat. ZN(40)/ZN(20), IP=0
P01AF810· 2.2 t
€11.84
€5.38/t
2.2 t / 1 m3 parent
Excav.hidr.neumáticos 100 CV
M05EN030· 0.04 h
€1.90
€47.57/h
0.04 h / 1 m3 parent
Camión basculante 4x4 14 t.
M07CB020· 0.12 h
€4.40
€36.65/h
0.12 h / 1 m3 parent
Motoniveladora de 135 CV
M08NM010· 0.03 h
€1.40
€46.65/h
0.03 h / 1 m3 parent
Rodillo vibr.autopr.mixto 15 t.
M08RN040· 0.03 h
€0.98
€32.80/h
0.03 h / 1 m3 parent
Cisterna agua s/camión 10.000 l.
M08CA110· 0.03 h
€0.86
€28.80/h
0.03 h / 1 m3 parent
km transporte zahorra
M07W020· 30 t
€3.30
€0.11/t
30 t / 1 m3 parent