Pre-Engineered Arch 5,75x3,9
- Code
- U03BE030
- Public ID
- OCf210381b14
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Components sum €1,276.29 · Unit price €1,276.29/m
Capataz
O01A020· 0.9 h
€16.17
€17.97/h
0.9 h / 1 m parent
Oficial primera
O01A030· 2.6 h
€46.05
€17.71/h
2.6 h / 1 m parent
Peón ordinario
O01A070· 3.473 h
€57.93
€16.68/h
3.473 h / 1 m parent
Bóveda H.A. 5,60x3,00 m 3,64 t/m
P02TB110· 1 m
€887.44
€887.44/m
1 m / 1 m parent
L.oxiasf.3kg/m2 LO-30-FV(60g/m2)
P06BL030· 1.1 m²
€3.56
€3.24/m²
1.1 m² / 1 m parent
Lámina geot. PP-110 g/m2
P06BG250· 3 m²
€2.10
€0.70/m²
3 m² / 1 m parent
Tablero encofrar 17 mm. 4 p.
M12EM040· 0.4 m²
€0.89
€2.22/m²
0.4 m² / 1 m parent
Zahorra natural sin clasif. IP<6
P01AD050· 21.34 t
€107.77
€5.05/t
21.34 t / 1 m parent
Grúa telescópica autoprop. 25 t.
M02GE020· 1.3 h
€135.42
€104.17/h
1.3 h / 1 m parent
Rodillo v.dúplex 55cm 800 kg.man
M08RL010· 0.436 h
€2.46
€5.64/h
0.436 h / 1 m parent
Rodillo vibr.autopr.mixto 7 t.
M08RN020· 0.175 h
€1.74
€9.94/h
0.175 h / 1 m parent
Retrocargadora neum. 50 CV
M05RN010· 0.175 h
€5.06
€28.94/h
0.175 h / 1 m parent
Hormigón HM-25/B/20/X0 central
P01HCM006· 0.1 m³
€9.70
€97.00/m³
0.1 m³ / 1 m parent