E04CZMI210Material
Sealing Fillings HM-25/F/20/XC2 Vertido Cubilote
Key Details
- Code
- E04CZMI210
- Public ID
- OCf2653626ca
- Category
- Materials
- Subcategory
- Unit
- m³
- Resource Type
- Material
- Last Updated
- July 30, 2026
Composition (BC3 recipe)
Components sum €123.86 · Unit price €125.51/m³
Oficial primera encofradores
O01BE010· 0.45 h
€8.38
€18.63/h
0.45 h / 1 m³ parent
Ayudante encofradores
O01BE020· 0.45 h
€8.02
€17.83/h
0.45 h / 1 m³ parent
Hormigón HM-25/B/40/XC2 central
P01HCM234· 1.1 m³
€106.70
€97.00/m³
1.1 m³ / 1 m³ parent
Vibrador hormig.eléctrico 70 mm.
M10HV060· 0.25 h
€0.76
€3.02/h
0.25 h / 1 m³ parent
Compare across the category