Lime mortar restoration / bronze 2mm rod
- Code
- R01RCR090
- Public ID
- OCf2d0a8fc62
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Components sum €84.41 · Unit price €84.76/m
Especialista reintegraciones e injertos
O01E030· 0.2 h
€4.11
€20.57/h
0.2 h / 1 m parent
AYUDANTE
O01A050· 0.1 h
€1.44
€14.40/h
0.1 h / 1 m parent
Especialista cosidos estáticos
O01E090· 0.3 h
€6.17
€20.57/h
0.3 h / 1 m parent
Peón especializado
O01A060· 0.3 h
€5.08
€16.93/h
0.3 h / 1 m parent
Mortero de restauración genérico
P34A320· 1 kg
€2.43
€2.43/kg
1 kg / 1 m parent
Adhesivo epoxi 100/35 o equivalente
P34A090· 0.05 kg
€0.85
€16.99/kg
0.05 kg / 1 m parent
Varilla bronce roscado D=6mm
P34OC020· 1.25 m
€8.06
€6.45/m
1.25 m / 1 m parent
Agua
P01DW010· 0.01 m3
€0.01
€0.91/m3
0.01 m3 / 1 m parent
Perforadora a rotación en seco
P34XB330· 0.2 h
€1.61
€8.07/h
0.2 h / 1 m parent
Pistola de inyección de mano
P34OE160· 1 ud.
€54.65
€54.65/ud.
1 ud. / 1 m parent