03HRM80220Material
Reinforced Concrete Wall Formwork HA-30/B/20/XC2 B500S en Continuous I/Enc. 2C. V/Bomba
Key Details
- Code
- 03HRM80220
- Public ID
- OCf35326a58b
- Category
- Materials
- Subcategory
- Unit
- m³
- Resource Type
- Material
- Last Updated
- July 27, 2026
Composition (BC3 recipe)
Components sum €679.18 · Unit price €731.95/m³
BOMBA DE HORMIGONAR
MB00200· 0.15 h
€8.38
€55.84/h
0.15 h / 1 m³ parent
ACERO EN BARRAS CORRUGADAS B400S EN CIMENT.
03ACC00011· 60 kg
€81.00
€1.35/kg
60 kg / 1 m³ parent
ENCOFRADO METÁLICO 2 C. EN MURO DE CONTENCIÓN
03ERT80060· 5.8 m²
€506.28
€87.29/m²
5.8 m² / 1 m³ parent
HORMIGÓN HA-30/B/20/IIa EN MUROS DE CONTENCIÓN
03HAM80060· 1 m³
€83.52
€83.52/m³
1 m³ / 1 m³ parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.