E10ECR010Material
Clamp bar of clay 25x8 cm
Key Details
- Code
- E10ECR010
- Public ID
- OCf8a88d177d
- Category
- Materials
- Subcategory
- Unit
- m
- Resource Type
- Material
- Last Updated
- July 30, 2026
Composition (BC3 recipe)
Components sum €6.44 · Unit price €6.44/m
Oficial primera solador/alicatador
O01BD010· 0.09 h
€1.73
€19.19/h
0.09 h / 1 m parent
Ayudante solador/alicatador
O01BD020· 0.09 h
€1.59
€17.68/h
0.09 h / 1 m parent
Rodapie barro 25x8 cm
P08ER060· 1.06 m
€2.95
€2.78/m
1.06 m / 1 m parent
MORTERO CEMENTO M-5
A01MA050· 0.001 m³
€0.09
€87.57/m³
0.001 m³ / 1 m parent
LECHADA CEM.1/2 CEM II/B-M 32,5R
A01AL020· 0.001 m³
€0.08
€82.31/m³
0.001 m³ / 1 m parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.