Rock Hard Basement Excavation with Explosives
- Code
- U02AD440
- Public ID
- OCfa36ee3ae3
- Category
- Materials
- Subcategory
- Unit
- m3
- Resource Type
- Unit price
- Last Updated
- August 3, 2026
Components sum €8.84 · Unit price €8.84/m3
Capataz
O01A020· 0.025 h
€0.45
€17.97/h
0.025 h / 1 m3 parent
Oficial primera
O01A030· 0.025 h
€0.44
€17.71/h
0.025 h / 1 m3 parent
Peón ordinario
O01A070· 0.025 h
€0.42
€16.68/h
0.025 h / 1 m3 parent
Goma-2 D=55 mm.
P01XG020· 0.15 kg
€0.50
€3.34/kg
0.15 kg / 1 m3 parent
Nagolita a granel
P01XN010· 0.3 kg
€0.37
€1.23/kg
0.3 kg / 1 m3 parent
Detonador eléctrico
P01XD010· 0.1 ud.
€0.13
€1.30/ud.
0.1 ud. / 1 m3 parent
Hilo de conexión
P01XC030· 1 m
€0.11
€0.11/m
1 m / 1 m3 parent
Cordón detonante 12 gr.
P01XC010· 0.015 m
€0.01
€0.49/m
0.015 m / 1 m3 parent
V.P.martillo en fondo hidr.150mm
M06VF120· 0.012 h
€2.61
€217.17/h
0.012 h / 1 m3 parent
Pala cargadora neumáticos 200 CV/3,7m3
M05PN030· 0.045 h
€3.07
€68.16/h
0.045 h / 1 m3 parent
Camión basculante 4x4 14 t.
M07CB020· 0.02 h
€0.73
€36.65/h
0.02 h / 1 m3 parent