E05AF020Material
Metal Plate / Compression Layer 5cm<4m Sheet 4mm
metalplatecompression5cm4m4mm
Key Details
- Code
- E05AF020
- Public ID
- OCfe9c6269be
- Category
- Materials
- Subcategory
- Unit
- m²
- Resource Type
- Material
- Last Updated
- July 30, 2026
Composition (BC3 recipe)
Components sum €27.25 · Unit price €28.92/m²
Oficial primera encofradores
O01BE010· 0.35 h
€6.52
€18.63/h
0.35 h / 1 m² parent
Ayudante encofradores
O01BE020· 0.35 h
€6.24
€17.83/h
0.35 h / 1 m² parent
Hormigón HA-25/F/20/X0 central
P01HCA071· 0.053 m³
€5.19
€98.00/m³
0.053 m³ / 1 m² parent
Plancha nervometal 4 mm.
P03AL030· 1.1 m²
€6.83
€6.21/m²
1.1 m² / 1 m² parent
ACERO CORRUGADO SOLDABLE B400 S/SD TALLER INDUSTRIAL+OBRA
E04AB040· 1.5 kg
€2.47
€1.65/kg
1.5 kg / 1 m² parent
Compare across the category
Item pages show one recorded price. The category guides carry the medians, ranges and source counts for Materials.